Installation Information
Installation Recommendations

Jobsite Storage and Handling

Laying Masonry Walls

Mortar Beds and Joints

Flashing of Masonry Work

Weep Holes and Vents


Cleaning Instructions
Sealers and Maintenance
Crack Control
Control Joint and
Joint Reinforcment
Wall Ties and
Joint Reinforcement
Tek Notes
 
Important: A full size sample panel complete with complementary mortar should be installed at the jobsite prior to installation of any PRAIRIE stone product. This panel will represent the quality, color and texture of the product and the workmanship to be expected for the project. Either the owner or the project architect must approve the panel. PRAIRIE stone will provide 4" units for a sample panel 4' x 4' at no cost for the material (not including freight to the site).

Limitations
The facing is not intended for use as an impervious surface.

Muratic acid should not be used as a cleaning agent or in direct contact with the facing.

The facing should not be continuously exposed to temperatures above 250° F.

Installation Recommendations
Cavity wall construction is recommended for exterior walls, with proper flashing, venting and weep holes.

A complementary or matching mortar color is recommended when using PRAIRIE stone units.

Control joint spacing should be approximately 20' maximum.

Continuous horizontal joint reinforcement is recommended every 16" or every course when installing 12" and 16" high units.

Keep walls clean by bagging or brushing during installation. This significantly simplifies cleaning. Avoid harsh cleaning methods after the walls have been erected as this may mar the surface of the units.